Guides / Consent to operate
Consent to operate: how it works
How a pollution board consent to operate (often called a CTO certificate) is granted and how long it lasts, taken from the Ministry of Environment's consent guidelines as amended in January 2026.
State Pollution Control Board. Sources last reviewed .
Key facts
Since 27 January 2026, when the amendment came into force, a consent to operate stays valid until it is cancelled: no expiry and no renewal. Under the 2025 guidelines it was five, ten or fifteen years for red, orange and green units, two more for blue.
“Once granted, the consent to operate shall continue to remain valid till it is cancelled in accordance with the provisions of paragraph 13 of these guidelines”
“12. In the said guidelines, paragraph 12 shall be omitted.”
“CTO, once granted, will remain valid until it is cancelled”
“They shall come into force on the date of their publication in the Official Gazette.”
“(d) Additional two years, in case of blue category”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 4, paragraph 4(3); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 12; PIB, "Government amends Uniform Consent Guidelines under Air and Water Acts", January 2026; Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 1(2); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 4(3). Checked .
The State Board decides a first consent to operate within 90, 60 or 30 days for red, orange and green units, counted from the date of a complete application; a case it has not decided goes to the State Level Monitoring Committee.
“from the date of receipt of application in all respects”
“Grant or refusal of consent to operate, first time”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 8(1); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 8, Table; Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 8(2). Checked .
What it is
The State Pollution Control Board's consent to operate an industrial plant, under the Water and Air Acts.
“Every application for consent to establish or operate an industrial plant under section 25 of the Act shall be made in the Form set out under the First Schedule”
“CTO, once granted, will remain valid until it is cancelled”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 3, paragraph 3; PIB, "Government amends Uniform Consent Guidelines under Air and Water Acts", January 2026. Checked .
Who applies
The occupier of the industrial unit, once it is set up and ready to operate, to the State Board (in a Union territory, its Pollution Control Committee).
“the occupier is required to obtain consent to operate”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 11(1); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 2(h). Checked .
How to get it
Apply in Form II, with the fee the state or Union territory sets.
“Every application of consent to operate an industrial unit under section 25 of the Act shall be made in Form II”
“also shall be accompanied by the fee as specified by state government or Union territory Administration”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 11(2); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 3, paragraph 3. Checked .
The Board may send an officer to inspect the plant, or the applicant may engage a Registered Environment Auditor for the visit.
“On receipt of an application for consent, the State Board may depute any of its officers to visit and inspect any place or premises under the control of the applicant or the occupier”
Source: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 11(i), paragraph 11(3). Checked .
The State Board decides a first consent to operate within 90, 60 or 30 days for red, orange and green units, counted from the date of a complete application; a case it has not decided goes to the State Level Monitoring Committee.
“from the date of receipt of application in all respects”
“Grant or refusal of consent to operate, first time”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 8(1); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 8, Table; Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 8(2). Checked .
How long is a consent to operate valid?
Since 27 January 2026, when the amendment came into force, a consent to operate stays valid until it is cancelled: no expiry and no renewal. Under the 2025 guidelines it was five, ten or fifteen years for red, orange and green units, two more for blue.
“Once granted, the consent to operate shall continue to remain valid till it is cancelled in accordance with the provisions of paragraph 13 of these guidelines”
“12. In the said guidelines, paragraph 12 shall be omitted.”
“CTO, once granted, will remain valid until it is cancelled”
“They shall come into force on the date of their publication in the Official Gazette.”
“(d) Additional two years, in case of blue category”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 4, paragraph 4(3); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 12; PIB, "Government amends Uniform Consent Guidelines under Air and Water Acts", January 2026; Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 1(2); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, G.S.R. 85(E), 30 January 2025, paragraph 4(3). Checked .
The consent has no expiry, but the fee may have one: a state may charge a one-time fee covering 5 to 25 years, paid again for a further period once that runs out, and non-payment of a prescribed fee is a ground for cancelling the consent.
“may determine one-time fee for consent to operate for any duration of period of 5 to 25 years as may be applied for by the Project Proponent”
“non-payment of any prescribed fee”
Sources: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 5(i), paragraph 5(1); Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 13(ii), paragraph 13(2)(ix). Checked .
Not yet confirmed
Not published: Whether a consent granted before 27 January 2026, with a validity date printed on it, still lapses on that date.
Source: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 4. Checked .
Why it matters
With no expiry, a consent now ends only when the Board cancels it, so its record (number, date, plant and conditions) is what to keep, along with any fee period your state set.
“Once granted, the consent to operate shall continue to remain valid till it is cancelled in accordance with the provisions of paragraph 13 of these guidelines”
Source: Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Amendment Guidelines, 2026, G.S.R. 63(E), 23 January 2026, item 4, paragraph 4(3). Checked .
How SchemeClock helps
- Record each plant as its own company item (one consent per plant is how the app keeps them, not a rule), and open one application under it.
- Track the application stage by stage: applied, inspection, consent granted.
- Record the grant with the consent order's number. The expiry date is optional: leave it blank, as the rules now set none, and no expiry reminders are sent.
- Pay the fee for the next period: you add the date your state board set, and reminders follow 30, 7 and 1 day before it and the day after if it passes; marking it done asks for the next one. Whether a date printed on an older consent still applies is not settled; see Not yet confirmed.
- Consultants: one login holds each client as its own organisation.
- It files nothing. Applications stay with your state board, in your hands.
A summary of the authorities’ published sources as checked on . Not legal advice: the authority’s official notification always wins. Spotted something out of date? Tell us.